Restoring / Cleaning Up the Industrialized
  Mahoning River
 

OVERVIEW:  A Brief Description of the Mahoning River and the Restoration Project

     The Mahoning River begins near Winona in Columbiana County, a few miles southeast of Alliance, and flows through five counties of eastern Ohio (Columbiana, Stark, Portage, Mahoning, Trumbull) and one county in western Pennsylvania (Lawrence)*.  (See watershed map.)  The Mahoning River joins the Shenango River in western Pennsylvania to form the Beaver River which flows into the Ohio River (see the US map).   The “upper elevation of the river”— Alliance to Leavittsburg—is the portion that is more rural and did not experience heavy industrial use and is, therefore, not heavily contaminated.   The mainstem (“lower elevation”) of the Mahoning River—northwest of Warren to its confluence with Shenango River at Mahoningtown, Pennsylvania (near New Castle)—was heavily contaminated by household waste until 1965 and the numerous steel mills and manufacturing plants that used the river as an “industrial sewer” for almost 100 years.  Toxins from that use have settled in the sediment in the riverbed and banks.  Research must be done to investigate removing and treating the sediment in order to restore the river. The US government has issued orders to the US Army Corp of Engineers for “ecological restoration of the river” from Warren to Lowellville, Ohio (the mainstem of the river in Pennsylvania did not experience as much pollution as the mainstem river in Ohio).  The cleanup of the industrialized Mahoning River is referred to as “The Mahoning River Ecological Restoration Project” and is described more fully below.   

* The tributaries of the Mahoning River travel through eight counties (Columbiana, Stark, Portage, Geauga, Ashtabula, Trumbull, Mahoning, and Lawrence), but the Mahoning River travels through only six counties.

 CONTENTS  

1. Background:  Information About the Mahoning River, its location, and what toxins are in it that need to be removed.  
2. Descriptions of Phases: There are four phases to this project; each has specific tasks.  
Phase 1:  Reconnaissance (1997 – 1999)
Phase 2:  Feasibility (2002 – 2004)
Phase 3:  Pre-construction (2005 – 2006)
Phase 4:  Construction (2007 – 2017)  
3. Resources  

Background:

     The Mahoning River was polluted during the nineteenth and twentieth centuries by two major sources:  the steel industries and the human population (the lack of waste water treatment plants alongside the Mahoning River until the 1960s also contributed to the river's pollution; until 1965, raw sewage from homes and businesses went directly into the river).

     The industrialized Mahoning River is the section of the waterway that was used by steel mills and factories.  It includes approximately 30 miles of the river—starting just west of Warren in Leavittsburg and continuing southeast to Lowellville , Ohio at the border of Pennsylvania .  There are 10 low-head dams in this area of the river.  These dams were built by the steel industries to increase the amount of water in front of each mill complex in order use it to cool the hot steel and machinery (that water, which after being used was often 100 degrees and filled with chemicals, was poured directly back into the river).  Over decades of this practice, most of the toxins from the steel mills were washed downstream to the Beaver and Ohio Rivers , while some of the toxic sediments settled on the bottom of the Mahoning River and accumulated in large amounts behind these low-head dams.

     Estimates provided by the Ohio EPA and US Army Corps of Engineers explain the scope of the cleanup/restoration project.  There are approximately 462,000 cubic yards of contaminated riverbed sediments.  Along the shore in the banks, there is an additional 286,000 cubic yards of contaminated sediments. This gives a total of 750,000 cubic yards of material spread out over a span of 30 miles to be cleaned up.

     The Mahoning River presents some complex problems to scientists and engineers.  Only 45% of the contaminated sediment is in one location:  behind the Girard Dam.  The other 55 % of contaminated sediment is spread out over those 30+ miles.  The dispersed nature of the deposits of sediment calls for numerous studies and the development of varying approaches for removal of the sediment and its disposal after removal.  The contaminated sediment on the river bottom could be dredged or capped.  The sediment that is removed will either go to a landfill or will be bioremediated. 

The riverbanks are another story.  Most often, where the river bends, deposits of mud and silt have built up and that newer, less toxic sediment has covered over the contamination allowing for growth of trees.  To simply remove the trees and dirt would expose the upper banks and cause erosion.  On the other hand, to leave the contamination under the banks runs the risk of potential exposure and seepage.  Such an exposure could easily happen when trees fall and their roots expose the contamination below.  That would allow contaminants into the river.  Treating this contamination may require the technological solution of bioremediation.

            Just how “toxic” or “hazardous” is the Mahoning?  (See River Contamination for a full description.)

Descriptions of Four Phases of the Mahoning River Ecological Restoration

Phase 1:  Reconnaissance, 1997 – 1999  
 Investigate and document problems for ecosystem restoration)  
Phase 2:  Feasibility, 2002 – 2004  
(Analyze impacts – environmental, socioeconomic, and engineering—and decide the methods to be used in restoration)  
Phase 3:  Pre-construction, 2005 – 2006  
(Prepare detailed design reports, plans and specifications)  
Phase 4:  Construction, 2006 – 2017  
(Restoration of the river)  
 Project Completed:  Estimated 2017  

 Phase 1:  Reconnaissance (1997 – 1999) 
     This phase was completed in 1999 by the US Army Corps of Engineers.   The objective was to address the problems and opportunities for ecosystem restoration related to contaminated sediments in the lower, industrialized Mahoning River (Leavittsburg to Lowellville).  Work for this study includes an evaluation of existing technical and historical data, the collection of new data, and the analysis of all the data.

     The objective of this study was to investigate the current condition of the river and riverbanks, identify where most of the pollution has settled, and to verify the need to restore the Mahoning River.

     The study demonstrated that the Mahoning River restoration was needed and that the feasibility study should commence.  

Phase 2:  Feasibility (2002 – 2004) 
    
A feasibility study is now in progress and investigates how the restoration should be done, how much it will cost, and who will pay for it.  Many impacts will be analyzed during this study:  environmental, socioeconomic, and engineering.  The current estimation for Mahoning River restoration is about $100,000,000; $65,000,000 will be paid for by the U.S. government, while the funds from the other $35,000,000 can come from the State of Ohio and local communities along the Mahoning River.

     During this phase, important decisions will be made as to exactly how the Mahoning River will be restored.  Disposal of the sediment remains an important unanswered question.  It will be wet, probably will require “dewatering” and may contain unacceptably high levels of toxins.   One solution might be to establish disposal sites along the river to detoxify the toxic sediment by using bioremediation.  Before returning the sediment water to the river, it too will need to be treated at wastewater treatment plants.  To construct new wetlands and apply bioremediation for the restoration would provide permanent filters for water entering the river—including storm-water or outflows from sewers.  Wetlands would replace the original ones that were lost over the last century through excavation along the river corridor or channelization of the river by industries.  They could become public recreational lands. 

     The work of Phase 2, the Feasibility Phase, is projected to be done in 2004 and includes these tasks.

  • Gather more samples and information to check for toxins in the river channel and near-shore areas.
  • Study and decide on the correct methods or combinations of methods to be used for restoration (i.e.:  look at all the specific details and decisions about dredging, encapsulating, bioremediation, excavation and stabilization, treatment of water resulting from any dredged material and disposal or beneficial use of material that is dredged, excavated, or bioremediated, etc.)
  • Estimate how gas, water, sewer or electric lines will be affected by the restoration project and decide where relocation is required. 
  • Survey the banks and make plans that minimize the toll on wildlife and the riverside forest as well as the erosion of soil on the bank, when construction is performed that will remove the earth on and under the banks that are saturated with oil and grease.
  • Decide how the substrate, the bottom of the river, will be restored.  

Phase 3:  Pre-construction (2005 – 2006) 
     This phase includes the pre-clean-up activities of engineering and design.  A Design Project Cooperative Agreement (PCA) will be signed, which initiates a two-phase project:  the preparation of detailed design reports as well as plans and specifications.  The cleanup, itself, will take ten years and will deal with approximately 750,000 cubic yards of material that is spread out over 34 miles.  Given the scope of the overall cleanup project, very special planning is required.  This will commence in 2005 and end in 2006.

Carmen Rozzi, Army Corp of Engineers and project manager for the Mahoning River restoration offers this technical description of Phase 3: 

“By removing the contaminated sediments we are creating a new sectional template throughout the study reach.  We don't do this haphazardly; various items need to be investigated and designed.  Hydrological and Hydraulic design is required to establish existing conditions and for determining the new conditions in accordance with the various plans for removing the sediments we will be investigating [in Phase 2.]  Additionally, geotechnical characterization needs to be accomplished along the reach. Removal and remediation techniques need to be explored. Settling ponds for temporarily storing and bleeding off the excess water prior to removal to an off-site location need to be designed; treatment of bleed-water needs to be designed. Cost engineering estimates need to be developed for each alternative investigated… a variety of items too numerous to mention need to be accomplished.”     

Phase 4:  Construction (2007 – 2017) 
     Finally, the restoration begins.  Sometime in 2007, the methods selected in Phase 2 and plans developed in Phase 3 will be enacted.  The restoration itself will occur in stages, beginning in Trumbull County with the Warren “pools” (small reservoirs on the river formed by low-head dams), then Upper Girard, Lower Girard, and moving into Mahoning County to the Youngstown/Campbell pools and completing in Struthers/Lowellville pools.  During this process, the river bottom would be severely disturbed, adversely affecting the plants and animals that are living in the river.  However, throughout this section of the river, the plants and animals are already severely adversely affected by toxic sediments and impoverished habitat diversity.  In order to restore ecological function to the river, habitat diversity must be restored.  That will happen as the sediments now covering the river bottom are replaced by a diversity of substrates.  

Project Completed:  estimated 2017 
 
     In the end, the Mahoning River will flow with much cleaner water and the contact ban will be removed and people will be able to fish, boat, and recreate in and along the river.  The river is expected to support a healthy fish population again (See “Fish Report” & “Future Recreation Once the River is Restored”).  Five of the low-head dams will be either removed or modified; perhaps fish ladders will be installed.  Some of the riverbanks and riparian zone will be restored; new wetlands will be created.  Between now and completion, the many phases of the project may change as technology advances.  The river restoration should be completed in 2017.

Resources:  


Environmental Protection Agency 
River corridor and wetland restoration principles http://www.epa.gov/owow/wetlands/restore/ Principles for the Ecological Restoration of Aquatic Resources   http://www.lakemerced.org/homepage.html  

US Army Corps of Engineers
http://www.lrp.usace.army.mil/pm/mahonoh.htm (high level project description from Army Corp of Engineers)  

The Ecological Restoration of the Hudson River
A look at the Hudson River and its restoration from PCBs released by General Electric.  (PCBs are also a pollutant in the Mahoning River .)  http://www.nywea.org/
 

From the US Fish & Wildlife Service, Division of Environmental Quality:  This case addresses natural resource injuries that have occurred due to the release of hazardous substances, particularly polychlorinated biphenyls (PCBs), to the Hudson River, primarily from General Electric’s Hudson Falls and Fort Edward, New York manufacturing plants.   http://contaminants.fws.gov/restorationplans/HudsonRiver.cfm  

The NYS Department of Environmental Conservation (DEC), National Oceanic and Atmospheric Administration (NOAA), and US Fish and Wildlife Service (FWS) are developing restoration options for Hudson River natural resources injured by PCBs and other hazardous substance contamination.    http://www.darp.noaa.gov/neregion/hudsonr.htm 

How One Person is Making a Big Difference 
An inspiring story about one young man and his growing efforts to clean the Mississippi and Ohio Rivers.  http://www.cleanrivers.com/
http://www.americanrivers.org/groupoftheweek/chadpregracke.htm

Academy of Natural Sciences' Institute for River Restoration
The Institute for River Restoration is an interdisciplinary group within the Patrick Center for Environmental Research that seeks to advance the science of restoration ecology and the application of effective watershed restoration practices.
 http://www.acnatsci.org/research/pcer/institute.html

Support for this project provided in part by the Ohio Board of Regents' Urban University Program

YSU Public Service Institute, One University Plaza, Youngstown, Ohio 44555-3355. This site created by Carol Trube, September 2001. Contact us: urban-studies@cc.ysu.edu with questions regarding this site.  Contact the Project Coordinator   regarding the Mahoning River Watershed project This website is funded by a grant from US EPA and Ohio EPA.

Hit Counter Visitors since February 2003